The Parallel Shaan-Jing Pipeline was completed and put into operation on 20 July 2005.
The Parallel Shaan-Jing Pipeline is supplied from the Sulige Gas Field and it starts from the gas processing plant Yulin, Shaanxi. The pipeline runs via Shijiazhuang to Beijing. By the Ji-Ning branch between the Qingshan and Anping distributing stations the Parallel Shaan-Jing Pipeline is connected to the West–East Gas Pipeline. It is also connected with the underground gas storage of Dagang Oilfield by Gang-Jing line and Gang-Qing line.
The length of the Parallel Shaan-Jing Pipeline is 935 kilometers (581 mi). It has a diameter of 1,016 millimeters (40 in) and designed pressure of 10 MPa. The capacity of the Parallel Shaan-Jing Pipeline is 12 bcm.
The Parallel Shaan-Jing Pipeline is operated by PetroChina.
Shenmu Skid-mounted Metering and Regulating Gate Station
NO. | Project Title | Product name | Pressure level | Number of suppliers | Annual operation |
1 | Parallel Shaan-Jing Pipeline Shenmu Gate Station | Metering and Regulating System | ANSI300 | 2sets | 2004 |
2 | Parallel Shaan-Jing Pipeline Shenmu Distribution Station | Metering and Regulating System | ANSI600 | 2sets | 2004 |
3 | Parallel Shaan-Jing Pipeline Jingping Distribution Station | Metering and Regulating System | ANSI600 | 2sets | 2005 |
4 | Parallel Shaan-Jing Pipeline Luquan Gate Station | Metering and Regulating System | ANSI600 | 8sets | 2005 |
5 | Parallel Shaan-Jing Pipeline Luquan Gate Station | Pressure Regulating System | ANSI600 | 8sets | 2005 |
6 | Parallel Shaan-Jing Pipeline Transportation-Increasing Project | Pressure Regulating System | ANSI600 | 9sets | 2009 |
7 | Parallel Shaan-Jing Pipeline Dagang Distribution Station | Pressure Regulating System | ANSI600 | 2sets | 2010 |
8 | Valve Room Distribution Reconstruction Project of the First and Parallel Shaan-Jing Gas Pipeline | Pressure Regulating System | ANSI600 | 33sets | 2011 |
9 | Yanchang Gas Field No.1 Well Area Natural Gas Development Sewage Treatment Plant Project | Metering and Regulating System | ANSI300 | 1set | 2011 |
10 | Ying Town, Jin Sha Tan Distribution Station Reconstruction Project | Ultrasonic Metering System | ANSI400 | 3sets | 2011 |
11 | Ying Town, Jin Sha Tan Distribution Station Reconstruction Project | Metering System | ANSI400 | 1Lot | 2011 |
12 | Shijiazhuang Compressor Station Regulating System Reconstruction Project | Metering and Regulating System | ANSI600 | 2sets | 2012 |
13 | The Fourth Shaan-Jing Pipeline Datang Coal-based Natural Gas Branch Project | Pressure Regulating System | ANSI600 | 6sets | 2012 |
14 | Dagang Station Turbine Metering Project of Beijing Huayou Gas Co., Ltd | Turbine Metering System | | 1set | 2012 |